│ Tutorial: Resources │
└─────────────────────────────────────────────────┘
In this lesson you:
■ add a resource to the Resource list
■ allocate a resource to a task
■ check the Loading graph for a resource
■ correct a resource overallocation
──────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1204
A resource is something used during a
project. A resource is ~used~2, but not
~used up~2--unlike materials such as nails
and paint. Examples of resources include
people, a conference room, and a machine.
Part of building a project is making a
list of available resources. Since all
projects in one subdirectory use the
same Resource list, HPM can point out
resource conflicts across projects.
────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1416
To create or edit a Resource list, you select
~Resources~2 from the Main Menu.
────────────────────────────────────────────────
Type ~6~2><CMD>
<XFLD>6<XFLD><CHOME><CMD><*1413
This is the Resource list. The tutorial already
has included some resources for your project. You
need to add one more--a carpenter. You start by
moving the cursor to the bottom of the list.
─────────────────────────────────────────────────
Press Ctrl-End><CMD>
<XFLD><CEND><XFLD><CMD><*1813
Now move to the new resource line.
──────────────────────────────────
Press Down Arrow><CMD>
<XFLD><DN><XFLD><CMD><*1815
Add your full-time carpenter to the list.
──────────────────────────────────────────
Type ~Carpenter~2 and press Tab><CMD>
<XFLD>Carpenter<TAB><XFLD><ENDDEF><CMD><*0815
The cursor is now in the Quantity column. When you add people to
the Resource list, the Quantity refers to the number of people,
not the number of hours they work. A full-time worker is 1.
─────────────────────────────────────────────────────────────────
Press Tab><CMD>
<XFLD><TAB><XFLD><ENDDEF><CMD><*1815
Now tell HPM the cost of the resource for each
time unit. The carpenter earns $12 per hour.
───────────────────────────────────────────────
Type ~12.0~2 and press Tab><CMD>
<XFLD>12.0<TAB><XFLD><ENDDEF><CMD><*1815
Next you indicate the time unit used to measure the
cost of the resource. The carpenter is paid hourly.
───────────────────────────────────────────────────
Type ~Hrs~2 and press Tab><CMD>
<XFLD>Hrs<TAB><XFLD><ENDDEF><CMD><*1215
Here you can add the name of a calendar created for this
resource -- so that HPM can take into consideration the
carpenter's vacation or other holidays.
────────────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1215
You create resource calendars just like you created the
project calendar back in Lesson 2. For now, just move on.
──────────────────────────────────────────────────────────
Press Tab><CMD>
<XFLD><TAB><XFLD><ENDDEF><CMD><*2215
Use this column for resources that earn overtime.
The carpenter earns $18 per hour for overtime.
─────────────────────────────────────────────────
Type ~18.0~2 and press Tab><CMD>
<XFLD>18.0<TAB><XFLD><CMD><*2215
At HiTech, the carpenter can work four hours of
overtime per day. Enter the daily overtime hours.
──────────────────────────────────────────────────
Type ~4~2 and press Tab><CMD>
<XFLD>4<TAB><XFLD><ENDDEF><CMD><*2215
The name or job title of the person
responsible for the resource goes here.
───────────────────────────────────────
Type ~MaintMgr~2 and press Tab><CMD>
<XFLD>MaintMgr<TAB><XFLD><CMD><*0415
Use a ~code~2 to group resources in various ways. If resources are
in different departments, you can assign a code to each department.
Then you can print a report for each department by using the code.
───────────────────────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*2215
Like the responsible column, the code column is
optional. You omit it and move to the next column.
───────────────────────────────────────────────────
Press Tab><CMD>
<XFLD><TAB><XFLD><CMD><*1215
The ~Description~2 column is optional, too. It lets you
add more information about your resources. You tell HPM
you're done and end up back at the Resource name column.
─────────────────────────────────────────────────────────
Press Enter><CMD>
<XFLD><ENTER><XFLD><ENDDEF><CMD><*1815
You complete the Resource list just as the
unexpected happens -- the carpenter resigns.
As a cost-saving measure, you decide not to
replace him.
─────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1815
You have to delete the resource from the list.
Use the Edit menu.
──────────────────────────────────────────────
Press F4><CMD>
<XFLD><F4><XFLD><ENDDEF><CMD><*0815
Select ~Remove resource~2.
───────────────────────
Type ~2~2><CMD>
<XFLD>2<XFLD><ENDDEF><CMD><*0815
HPM displays a fill-in.
First, clear it.
───────────────────────
Type Ctrl-E><CMD>
<XFLD><CtrlE><XFLD><ENDDEF><CMD><*0815
Now type the name.
───────────────────────
Type ~Carpenter~2><CMD>
<XFLD>Carpenter<XFLD><ENDDEF><CMD><*0815
The fill-in is complete.
────────────────────────
Press F10><CMD>
<XFLD><F10><XFLD><CMD><*1214
HPM deletes the resource from the
list. Now you can leave the
Resource list and ~allocate~2 a
resource to a task. Return to the
Main Menu.
───────────────────────────────────
Press Esc><CMD>
<XFLD><ESC><XFLD><CMD><*1218
The Tutorial will get the Hitech1 project for you.
──────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF>
5<F2><ENTER>HITECH1 <F10><F10><CHOME><CMD><*1413
Planning the booth is a big job, and several
people will be involved. You want to see
the resources allocated to ~Plan~2. First,
use the speed key for Find task.
────────────────────────────────────────────
Press Ctrl-F><CMD>
<XFLD><CtrlF><XFLD><ENDDEF><CMD><*0411
HPM displays a fill-in for
the task name. First, you
clear what's there.
──────────────────────────
Type Ctrl-E><CMD>
<XFLD><CtrlE><XFLD><ENDDEF><CMD><*0411
Now type the task's name.
──────────────────────────
Type ~Plan~2 and press F10><CMD>
<XFLD>Plan<F10><XFLD><ENDDEF><CMD><*0411
You want to look at the
~Allocations list~2. Use
its speed key.
─────────────────────────────
Press Ctrl-R><CMD>
<XFLD><CtrlR><XFLD><CMD><*1212
You want to add a resource to this
list. You decide to allocate the sales
assistant to this task. Type the name
and move to the next column.
──────────────────────────────────────────
Type ~SalesAsst~2 and press Tab><CMD>
<XFLD>SalesAsst<TAB><XFLD><ENDDEF><CMD><*1214
The Quantity is 1.000 for a person.
───────────────────────────────────
Press Tab three times><CMD>
<XFLD><TAB><TAB><TAB><XFLD><ENDDEF><CMD><*1214
The sales assistant will spend
5 days on this task.
───────────────────────────────
Type ~5~2 and press Enter><CMD>
<XFLD>5<ENTER><XFLD><ENDDEF><CMD><*1212
The ~R~2 at the extreme left
means an overallocation. Now
return to the PERT chart
of your project. Use the
speed key to switch views.
────────────────────────────
Press Ctrl-V><CMD>
<XFLD><CtrlV><XFLD><CMD><*1213
HPM is warning you that you overallocated
a resource. Look for the word ~Resource~2 at
the lower left of this screen.
──────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1212
Check the loading graph to see how serious the
problem is. First pull down the Graphs menu and
then select ~Resource loading~2.
───────────────────────────────────────────────────
Press F2 and type ~8~2><CMD>
<XFLD><F2>8<XFLD><CMD><*4103
The horizontal line shows
how much of the resource
is available (1.0).
─────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*4103
The shaded part above it
shows how much time the
resource is allocated to
work beyond the time
available.
──────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*4103
For another view of resource
overallocation, check the
Resource allocations graph.
─────────────────────────────
Press F2 and type ~9~2><CMD>
<XFLD><F2>9<XFLD><CMD><*0813
On the left, you see the names of the
project tasks the Sales Assistant is
allocated to. The letter ~R~2 means
an overallocation.
──────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1212
The shaded bars show when the
resource is allocated. The
Sales Assistant is supposed
to work on two tasks at once.
─────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*0811
Now that you know the extent of
the problem, you can correct the
overallocation. Or you can let
HPM correct it automatically.
Pull down the Compute menu.
────────────────────────────────
Press F6><CMD>
<XFLD><F6><XFLD><ENDDEF><CMD><*0814
Now try out the automatic resource
leveling feature. Select ~Level~2
~resources~2.
──────────────────────────────────
Type ~4~2><CMD>
<XFLD>4<XFLD><ENDDEF><CMD><*0814
HPM displays this warning before
leveling resources. Go ahead.
─────────────────────────────────
Press F10><CMD>
<XFLD><F10><XFLD><ENDDEF><CMD><*0813
Notice that the ~R~2s are gone.
The bars aren't overlapping.
Recruiting has been postponed.
───────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1214
Now return to the PERT chart.
Use the speed key.
──────────────────────────────
Press Ctrl-P><CMD>
<XFLD><CtrlP><XFLD><CHOME><CMD><*0414
Find the Task form for
the task ~Recruit~2.
───────────────────────
Press Ctrl-F><CMD>
<XFLD><CtrlF><XFLD><ENDDEF><CMD><*0414
Clear the fill-in and type
the task name.
───────────────────────────
Press Ctrl-E and
type ~Recruit~2><CMD>
<XFLD><CtrlE>Recruit<XFLD><ENDDEF><CMD><*0414
Confirm it.
─────────────────────
Press F10><CMD>
<XFLD><F10><XFLD><ENDDEF><CMD><*0414
Use the Task form's speed key.
──────────────────────────────
Press Ctrl-T><CMD>
<XFLD><CtrlT><XFLD><CMD><*1016
Find the ~Pln start~2 field. Look
for the small symbol that looks like
an arrow pointing left and right.
─────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1016
The double arrow symbol shows a date
that was changed during automatic
resource leveling.
────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1013
HPM made the start date later to avoid
overallocating a resource. You're not
satisfied, because you don't want to
wait that long to begin recruiting.
───────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1016
Now erase the dates HPM has
changed by leveling. Start
by removing the task form.
─────────────────────────────
Press Esc><CMD>
<XFLD><ESC><XFLD><CMD><*0410
Press F7
and then
Enter.><CMD>
<XFLD><F7><ENTER><XFLD><ENDDEF><HOME><CMD><*0410
Press the
End key
and then
press F10.><CMD>
<XFLD><END><F10><XFLD><ENDDEF><CMD><*1213
The resource overallocation is back. This
time you're going to change the allocation,
so that the Sales Assistant doesn't work
on the task Plan.
───────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1214
Move the cursor to the task ~Plan~2.
───────────────────────────────────────
Press Up Arrow twice><CMD>
<XFLD><UP><UP><XFLD><ENDDEF><CMD><*1214
To see the Allocations list again,
use the speed key.
──────────────────────────────────
Press Ctrl-R><CMD>
<XFLD><CtrlR><XFLD><CHOME><CMD><*0712
The ~R~2 beside SalesAsst
is back. Use the speed
key to remove the
allocation.
──────────────────────
Press Ctrl-X><CMD>
<XFLD><CtrlX><XFLD><ENDDEF><*0415
You're already at the correct
resource, so just confirm it.
─────────────────────────────
Press F10><CMD>
<XFLD><F10><XFLD><ENDDEF><*1214
Now recalculate the project.
─────────────────────────────
Press Ctrl-C><CMD>
<XFLD><CtrlC><XFLD><ENDDEF><*1214
The warning ~Resource~2 has
disappeared from the bottom of
the screen. Now return to the
Main Menu.
──────────────────────────────
Press Esc><CMD>
<XFLD><ESC><XFLD><CMD><*1214
One more time...
──────────────────────────────
Press Esc again><CMD>
<XFLD><ESC><XFLD><CMD><*1218
Now review this lesson.
──────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1204
~In summary ...~2
■ Add resources to the Resource list.
■ Allocate resources to the tasks
they'll work on.
■ View Resource loading and
Resource allocations graphs.
■ Correct a resource overallocation.
──────────────────────────────────────────────────
Press Space bar><CMD>